2018
Completion Date
$600 million
Project Value
45,000 m3
Concrete Pumped
Location: Grey Street, South Brisbane QLD
Main Contractor:
Watpac Construction / Hutchinson Builders
Equipment Used:
1 x Schwing SPB37 Separate Placing Boom
1 x Schwing SPB30 Separate Placing Boom
1 x Putzmeister MX36 Separate Placing Boom
1 x Putzmeister 2110 HP-D High Pressure Stationary Line Pump
2 x Putzmeister 2109HD High Pressure Stationary Line Pump
Various Mobile Pump Units as required
Vertical Pumping Height:
99m